Metalloinvest will allocate more than 50 billion rubles for a comprehensive maintenance and repair program in 2025.

This is the largest MRO program in the company's history, which will ensure the technological sustainability of production.

Shop of hot briquetted iron No. 2 Lebedinsky GOK. Photo: "Metalloinvest".

Work is being carried out at all Metalloinvest enterprises in accordance with approved schedules. Resource plans are developed for each project, taking into account the availability of personnel, spare parts and components.

The most intense period of the repair campaign is traditionally the second half of the year.

In August 2025, the Lebedinsky GOK has already overhauled the complex for the production of hot briquetted iron No. 1 (GBZH-1). In September – October, the GBZH-2 and GBZH-3 complexes, as well as the roasting machine No. 4, will undergo major repairs.

Roasting machine No. 3 will be repaired at Mikhailovsky GOK.

Mill 700 of the rolling mill No. 1 at the Oskolsky Electrometallurgical Combine named after A.

A. Ugarov. Photo: "Metalloinvest".

Oskol Electrometallurgical Combine will have an extensive overhaul program in September and December: work will take place in the rolling mill No. 1, including mill 700, heating furnace No. 3, homogenization furnace, as well as at the pelletizing and metallization factory, where metallization plants No. 3 and No. 4 will be repaired.

The large–scale production asset management program is part of Metalloinvest's strategic course to increase technological sustainability and further increase the efficiency of production processes.