UK Kuzbassrazrezugol ' increases train capacity


In the branch "Taldinskaya coal mine" of JSC "UK "Kuzbassrazrezugol" (enterprise resource complex UMMC) completed the construction of train loading path on machine-1 (includes coal storage, loading, one, two crushing and screening plants). For the project, the Company sent more than 60.5 million.





the New object is a complex of structures and special equipment designed to handle wagons and prepare for the transportation of coal. The two-storeyed building of the operator equipped computer Desk. Special software and hardware that allows to record and process the results of weighing the cars with the help of installed on the way of wagon scales "Vesta LED is 120.2". Here mounted installation clean cars from snow air, the complex irrigation of the cars in the winter protivosvertawati reagents, installing, leveling and compaction of the load to prevent contamination of the environment. The quality of shipped coal will be monitored through preobrazgenskiy machine that pulverizes coal and prepares samples for laboratory determination of quality indicators of the goods.





"the Total length of the new loading path - almost 650 metres. He will in the future not only significantly increase the volume of shipped products, but also enhance its quality control, - says the Deputy Director on capital construction of JSC "UK "Kuzbassrazrezugol" Eugene Buymov. – The site was built in less than six months. The decree issued a conclusion on the compliance of the project documentation".





Rail of the loading path on the tech corridor-1 is able to dispatch no less than 80 cars per day that will increase the daily loading of coal at 5 600 tonnes.