the Top Pyshma (Sverdlovsk oblast)
In the workshop of the copper powders of JSC "Uralelectromed" (metallurgical complex of UMMC) has started installation of process bridge crane used to service a series of electrolysis baths. The cost of the equipment along with installation amounted to 7 million rubles.
According to the chief plant copper powders Anton Davletshin, the new unit will replace an existing, worked for 20 years. It will provide reliable service 136 electrolysis baths and improve working conditions for drivers of the crane.
- crane workshop in a timely manner will perform the loading and unloading of anodes, cathode scrap, resulting in the process of electrolysis. Per shift crane operator will be able to serve about 35 electrolysis baths, he said.
Modern double girder overhead travelling crane in domestic production has the capacity of 5 tons. It consists of longitudinal beams with a length of 28.5 meters, trolleys with hook and motor. Unlike its predecessor, the office organized with the help of frequency converters. On tap will be installed a modern control room. The movement of the driver unit is controlled with joysticks.
to Complete the installation and commissioning work is scheduled at the end of II quarter of this year.
JSC "Uralelectromed" is one of Europe's leading and Russia's only producer of electrolytic copper powders. Method of electric refining company produces more than 20 brands of powder in accordance with GOST and technical conditions, constantly expanding the range. Technological line can produce copper powders in particle size from 5 to 600 µm.