Home / News / Engineering / For the first time, a prefabricated hot blast furnace gas regenerator assembled outside the plant

For the first time, a prefabricated hot blast furnace gas regenerator assembled outside the plant

Engineering

The new regenerator casing was manufactured at Danieli and installed at SSAB Sweden without the usual maintenance.

For the first time, a prefabricated hot blast furnace gas regenerator assembled outside the plant
Фото: В течение одного дня в SSAB Oxelösund была установлена ​​печь горячего дутья Danieli Corus

Earlier this week, a new hot blast furnace # 47 gas regenerator housing was installed for blast furnace # 4 at SSAB's Oxelösund plant in Sweden. The entire hull was completely fabricated off-site and set in working position with a single crane lift.

This is the first time Danieli has applied such a manufacturing solution to a blast furnace.

The installation was successful thanks to careful planning and a study with SSAB of the aboveground and underground infrastructure in the blast furnace area.

The applied innovative technology will pay off very quickly: all welding, coating and rigorous testing in the off-site workshop minimizes the amount of work performed on site, in more difficult conditions and in compliance with all factory regulations, and thus saves a significant amount of working hours.

This strategy provides greater efficiency in terms of supervision and logistics. The installation of hot blast furnace # 47 will now be completed with maximum efficiency.