800 tons of metal structures were lowered underground: Gaysky GOK is building a crushing and conveyor complex "Rudny trakt-2"

Press Releases
800 tons of metal structures were lowered underground: Gaysky GOK is building a crushing and conveyor complex "Rudny trakt-2"

Guy (Orenburg region)

Specialists of the Mine Construction Department of PJSC "Gaysky GOK" (an enterprise of the raw materials complex of UMMC) began construction of the crushing and conveyor complex "Rudny Trakt-2". The works are deployed deep underground - at elevations of 1275-1340 m of the underground mine. There will be a whole network of conveyor galleries and a crushing and batching complex designed for crushing and delivering ore from the lower horizons to the shaft of the "Operational" mine. Investments in the first stage of the project will amount to about 370 million rubles.

- Gaysky GOK "today mines ore below the kilometer mark. In order to involve the lower ore reserves in mining, a plan has been developed for the construction of the crushing and conveyor complex "Rudny trakt-2". The new facility should provide the output of ore in the amount of up to 4.5 million tons per year, - said the acting director. Nikolay Efimov, Chief Engineer of the Gaysky GOK.

At the main stage, the mine builders will erect several capital mining facilities. In general, according to the project, the crushing and conveyor complex "Rudny trakt-2" will consist of two main conveyors, four section conveyors, ten crushing complexes and a blending hopper with a feeder chamber for separating ore flows.

- On At the first stage of construction of this complex, the mine builders performed a very large and technologically complex scope of work. At a depth of more than a kilometer underground, they erected 800 tons of metal structures. For comparison, ten empty Boeig 767 aircraft weigh about the same! The length of the finished conveyor galleries will be about a kilometer, - said the head of the mining and control system Vadim Balakov.

After the completion of the construction of the crushing and conveyor complex "Rudny trakt-2", the crushed ore from the 1340-meter horizons will be transported by main conveyors to the reversing conveyor of the horizon 1275 meters for dividing ore streams into two storage bins. This will ensure uninterrupted operation of the batching and loading complex of the "Operational" mine shaft.

Since 2011, the Gaysky GOK has been carrying out large-scale reconstruction of the "Operational" mine. According to the construction plan, it should be commissioned in August 2019.