Within five days, the representative of the ANR, together with the specialists of PJSC "EMSS", carried out visual and measuring control of 10 large-tonnage workpieces intended for the equipment of the main circulation pumping unit and the steam generator of Blocks No. 3 and No. 4 of the Akkuyu NPP.
The products have passed the acceptance inspection in full, no inconsistencies in the production process have been identified, the control points according to the quality plans have been examined and signed. The received products are preserved and are being prepared for shipment to the Customer. At the end of the work, the commission signed all the documents confirming the successful acceptance of the products manufactured at EMSS.
The shipment of finished products is scheduled for November-December. The batch will include four flanges, three shells and three pipes.
Let us remind you that in 2020 Energomashspetsstal PJSC successfully passed the inspection of the Nuclear Regulatory Agency of the Republic of Turkey (ANR), which renewed the certificate of the manufacturer of blanks for the equipment of the Akkuyu NPP being built in the Republic of Turkey for the next five years - until January 2026 .