In April, JSC "Ukrenergomashyny" (former Kharkov plant Turboatom) shipped to the customer a modernized impeller for a hydraulic turbine of the type PL-15-GK-600 of the Kanevskaya HPP (station No. 17, Ukraine).
On an impeller with a diameter of 6 meters, the machine builders replaced the sliding rollers and carried out tests. The equipment was packed and sent to the station.
The amount of these works under the contract is UAH 7.5 million including VAT.
Kanevskaya HPP is the second stage of a cascade of hydroelectric power plants on the territory of Ukraine, in the city of Kanev, Cherkasy region, built on the Dnieper River and is part of Ukrhydroenergo.