In April, JSC "Ukrenergomashyny" (former Kharkov plant Turboatom) shipped to the customer a modernized impeller for a hydraulic turbine of the type PL-15-GK-600 of the Kanevskaya HPP (station No. 17, Ukraine).
On an impeller with a diameter of 6 meters, the machine builders replaced the sliding rollers and carried out tests. The equipment was packed and sent to the station.
Recommended:
The amount of these works under the contract is UAH 7.5 million including VAT.
Kanevskaya HPP is the second stage of a cascade of hydroelectric power plants on the territory of Ukraine, in the city of Kanev, Cherkasy region, built on the Dnieper River and is part of Ukrhydroenergo.