Repair work on the pipeline will take approximately 5 months and will cost 1.2 million.

DMK will repair the pipeline konstaninou mixture

On the Dnieper metallurgical plant starts performing major repairs of the gas pipeline Du-1220, which provides uninterrupted transportation konstaninou gas mixture in the production shops of the company.

Total length of the pipeline and 4 km from the overhaul includes plans to renovate its station in 1.5 km.

"in order to maintain the pipeline in good condition - no emergency stops needed capital in a timely manner to repair, on average once a year due to corrosion in the metal pipe of the pipeline there are defects and cracks as a result have witecki coke oven gas", - says Alexei Koval, head of the gas Department.

Repair is scheduled for 150 days. Be performed replacement of the worn metal of the pipeline, on processing sections of the pipe will be mounted special designs - napisali also planned to carry out repair of grounds maintenance and valves.

the overhaul Process control chief engineer - head of the UGE of the plant Oleg Pomogaev. The cost of the overhaul is about 1.2 million.

Pipeline operated since 1950. The overhaul will reduce leakage of the gas mixture, to increase the reliability of operation of the pipeline, improve economic and environmental performance, said the company.