At the moment, the specialists of the Kharkov enterprise have manufactured and handed over to the customer - PJSC "Ukrhydroenergo" - a hydraulic turbine impeller. By the end of this month, the equipment will be shipped to the station. We are also working on the shipment of guide vane parts.
In the first quarter, the following equipment was already shipped to the station: a turbine shaft, drainage and drainage systems, a set of loading and unloading devices.
In general, the completion of production of this unit is scheduled for the third quarter of 2021.
Also, work is underway on the hydroelectric unit st. № 5. Now the machining of the main parts for the assembly of the impeller and the guide vane is being completed.
The contract for the reconstruction of rotary-blade units at the Kremenchug HPP was concluded between Turboatom and Ukrhydroenergo on March 14, 2019. The subject of the contract is the reconstruction of two turbines and two generators of hydroelectric units at st. No. 4, 5, including design, manufacture, supply of equipment, performance of dismantling and installation works and engineering support services.