Home / Press Releases / At the processing plant Uchalinsky GOK have replaced the crushing plant

At the processing plant Uchalinsky GOK have replaced the crushing plant

Press Releases
At the processing plant Uchalinsky GOK have replaced the crushing plant


Uchaly (Republic of Bashkortostan)









At the processing plant Uchalinsky GOK (enterprise resource complex UMMC) installed a new cone crusher of secondary crushing production of JSC "Uralmashzavod" (KSD-2200Гр-Д1МУ). The equipment is suitable for crushing ore before processing it in concentrates.









the new hardware solutions aimed at improving performance and facilitating maintenance of the machine. The main advantage of the crusher – the automated system with a gear hydraulic control mechanism of the slit, allowing a continuous production cycle to maintain the desired size of crushed product and reduce the complexity of work when removing nodes during scheduled inspections.









the Automated control system enables real-time monitoring and diagnostics of all systems. "Automation of information-dilution crusher will greatly facilitate the labor of the workers, reduce the time of regulation of its parameters and will allow us to improve performance. Another plus – all the basic performance of the crusher will be displayed on the operator panel, allowing you to respond quickly to the slightest changes in the process," – said the mechanic in the crushing Department concentrator Ilshat Baigarin.









KSD-2200Гр-Д1МУ also equipped with a system of mechanical paleobotany without water supply, which prevents the ingress of dust into the friction, which greatly improves the resource machine.

















Performance cone crusher is 360-610 m3 of ore per hour. Installation and commissioning produced with the direct participation of specialists of the manufacturer.